How long does it take to design and consent a new home in Canterbury?

One of the first questions we’re asked is how long it takes to get from an idea to a consented home. Here’s what to expect at each stage, and what can speed things up or slow them down.

The short answer

Most new homes take around 6 to 9 months from the first meeting to an approved building consent, and it can be a lot shorter. The biggest factor is how quickly decisions are made. There are meetings throughout the process, and each stage moves on once you’ve signed it off. The council’s part is usually the shortest.

The table below shows the stages we work through. Times also depend on our workload and how each job fits into the schedule, so treat them as a guide.

Stage What happens Typical time
1. Brief and site visit We meet, walk the site and agree what you need, your budget and your priorities. Usually 1 day
2. Concept design Floor plans and sketches that show how the home sits on the site. Sometimes as short as a week
3. Developed design Materials, windows, structure and layout are refined. Depends on how many changes are made
4. Consent drawings Detailed drawings and specifications for the council and your builder. Engineers and other consultants come in at this stage. Around 4 to 6 weeks
5. Building consent The council reviews and approves the application. 20 working days, plus time for any council questions

How long does the council take?

Councils have 20 working days to process a building consent application. The clock stops whenever the council asks for more information and starts again when it’s answered, so the real time is often longer.

A complete, well-documented application is the best way to keep this stage short.

Will I need resource consent as well?

Some projects need resource consent before, or alongside, building consent. This is more likely if your site is rural, close to a boundary, in a hazard area or flood plain, or in a district with design or landscape controls, such as parts of Wanaka and Queenstown.

Resource consent adds time, and each district has its own rules. We’ll let you know early if your project is likely to need it. You’ll also find more answers on our FAQs page.

What slows a project down?

  • An open brief. Some clients know exactly what they want. Others are still deciding between a single or two-storey home. We work through that with you, but it adds time at the start.
  • Changing the brief late. Changes are easy at concept stage and expensive once consent drawings are under way.
  • Slow decisions. Each stage ends with your sign-off, so the longer it takes to respond, the longer the overall design will take. If a project goes on hold for a while, allow time for it to fit back into our schedule when you’re ready to go again.
  • Reports from other specialists. Geotechnical, engineering and survey reports all have their own lead times.
  • Council questions. These pause the 20-day clock.

How to keep your project on track

  • Agree a realistic budget before design starts.
  • Get a site survey and geotechnical report early.
  • Bring your builder in during design, if you have one in mind.
  • Set aside time to review drawings promptly at each stage.

To see what the finished result can look like, browse our residential projects.

Planning a new home?

The earlier we talk, the easier it is to plan around your timeline. Get in touch to start the conversation.